|
|
|
![]() |
|
|
|
September 29, 2022 |
|
Environmental & Social Monitoring report _K A Design |
|
|
|
September 1, 2022 |
|
Environmental & Social Monitoring report_K A Design |
|
|
|
September 1, 2022 |
|
NPCL- Observation report for environmental social and health safety compliance of Solar Irrigation Project (Operational) |
|
|
|
September 1, 2022 |
|
ESIA of 2.517 MWp Solar Roof-top Project of Fakhruddin Textile Mills Ltd. |
|
Fakhruddin Textile Mills Ltd. proposed a 2.517 MWp rooftop solar project on their rooftop. The project site is located at Gargaria, Master Bari under Sreepur Upazila within the Gazipur district under Dhaka Division. Sreepur is located in between 24°11'56" North Latitudes and 90°28'41.5" East Longitudes.
In the proposed system two main pieces of equipment will be used which are panels and inverters. Sun shines on the solar panels to generate DC electricity. The DC electricity produced from the solar panel will be converted to 440V 3-phase AC using the inverters. Then, the energy will be fed into the bus bars of industry. A Zero Export Controller will be used to ensure ‘Net Zero Export’.
This document is the Environmental and Social Impact Assessment (ESIA) assessment for a rooftop solar project on Fakhruddin Textile Mills Ltd.’s rooftop. The project proponent will create an Environmental and Social Management Plan (ESMP) as a part of the ESIA. The mitigation measures suggested, environmental and social monitoring and reporting requirements, emergency response procedures, related institutional or organizational arrangements, capacity development and training measures, implementation schedule, and performance indicators will all be included in the ESMP. Where impacts and risks cannot be avoided or minimized, mitigating measures and activities will be established in order for the project to be planned, constructed, and operated in accordance with applicable laws and regulations and to meet the requirements set forth in this document
|
|
 |
|
|
|
September 1, 2022 |
|
Environmental & Social Assessment of 369.0 kWp Solar Roof-top Project of Khantex Fashions Ltd. |
|
Khantex Fashions Ltd. proposed a 369.0 kWp rooftop solar project on their rooftop. The project is located at Barotopa, Mawna, Sreepur, Gazipur (24.208688 N, 90.373954 E).
In the proposed system two main equipment will be used which are solar panels and inverters. Sun shines on the solar panels to generate DC electricity. The DC electricity produced from the solar panel will be converted to 440V 3-phase AC using the inverters. Then, the energy will be fed into the bus bars of industry.
This document is the detailed Environmental and Social Assessment (ESA) study for the rooftop solar project on the rooftop of Khantex Fashions Ltd. As part of the ESA, the project proponent will prepare an Environmental and Social Management Plan (ESMP) that addresses the potential impacts and risks identified by the environmental and social assessment. The ESMP will include the proposed mitigation measures, environmental and social monitoring and reporting requirements, emergency response procedures, related institutional or organizational arrangements, capacity development and training measures, implementation schedule, and performance indicators. Where impacts and risks cannot be avoided or prevented, mitigation measures and actions will be identified so that the project is designed, constructed, and operated in compliance with applicable laws and regulations and meets the requirements specified in this document.
|
|
 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of Nutan Bidyut (Bangladesh) Limited_2021 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of Kushiara Power Company Limited_2021 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of DBL Industrial Park Limited_2021 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of City Edible Oil Limited_2021 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of City Seed Crushing Industries Limited_2021 |
|
|
|
April 27, 2022 |
|
Annual E_S Compliance Audit Report of Doreen Hotel & Resort Limited_2021 |
|
|
|
November 10, 2021 |
|
Environment & Social Impact Assessment of DBL Industrial Park Limited |
|
|
|
September 27, 2021 |
|
Environment & Social Impact Assessment of City Seed Crushing Industries Limited |
|
|
|
September 27, 2021 |
|
Environment & Social Impact Assessment of City Edible Oil Limited |
|
|
|
September 26, 2021 |
|
Environment & Social Impact Assessment of Robi Axiata Limited |
|
|
|
August 23, 2021 |
|
Environmental and Social Safeguards Framework Arrangement : Third PublicPrivate Infrastructure Development Facility Tranche 2 |
|
|
|
June 30, 2021 |
|
Annual E_S Compliance Audit Report |
|
|
|
June 30, 2020 |
|
Annual E_S Compliance Audit Report |
|
|
|
May 11, 2020 |
|
Environment & Social Impact Assessment of Sympa Solar Power Limited |
|
|
|
February 24, 2020 |
|
Addendum to Environment & Social Impact Assessment of NBBL |
|
|
|
September 17, 2019 |
|
ESIA report of Shun Shing Cement Industries Limited |
|
|
|
June 30, 2019 |
|
Annual E_S Comp. Audit Report |
|
|
|
March 28, 2019 |
|
Environment & Social Impact Assessment of Summit Communication Limited |
|
|
|
January 31, 2019 |
|
Environment & Social Impact Assessment of USA Agro and USA Auto Bricks Limited |
|
|
|
January 8, 2019 |
|
ESIA of Meghna Cement Mills Limited |
|
|
|
January 8, 2019 |
|
ESIA - Tosrifa Industries Limited |
|
|
|
December 10, 2018 |
|
ICS Field Observation report |
|
|
|
December 10, 2018 |
|
SIP- GAZI-EHS-Monitoring-report 'Observation report for environmental, social and health safety compliance of three Solar Irrigation Project (Operational) |
|
|
|
November 11, 2018 |
|
Environment & Social Impact Assessment of Kushiara Power Company Limited |
|
|
|
October 28, 2018 |
|
Battery manufacturing and recycling factory individual visit report - 2018 |
|
|
|
October 25, 2018 |
|
Final Environmental and Social Assessment for Solar System Project by Far East Industries LTD |
|
|
|
October 25, 2018 |
|
Final Environmental and Social Impact Assessment (ESIA) Solar Mini-grid at Chapainawabganj |
|
|
|
October 15, 2018 |
|
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT 250 kWp Standalone AC-DC Coupled Solar PV based mini grid power plant by Blue Marine Energy Limited at Saint Martin Island |
|
|
|
October 11, 2018 |
|
ESIA Report- 218.6kW Solar Mini Grid Project, Charsajai, Kodalkathi Union, Char Rajibpur Upazila, Kurigram District-Prepared By Connectia Limited |
|
|
|
September 23, 2018 |
|
Environment & Social Impact Assessment of Summit Alliance Port Limited |
|
|
|
September 12, 2018 |
|
Final Environmental and Social Impact Assessment (ESIA) _ Solar Mini-grid at Chapainawabganj _ Eastec Limited |
|
|
|
September 5, 2018 |
|
Environment & Social Impact Assessment of Summit Alliance Port Limited (Expansion) |
|
|
|
August 16, 2018 |
|
"Environmental and Social Management System (ESMS)" guideline for Solar Rooftop & Grid Tied Solar Power projects. |
|
"Environmental and Social Management System (ESMS)" guideline for Solar Rooftop & Grid Tied Solar Power projects.
- IDCOL has recently decided to provide financial and technical supports to solar rooftop and grid-tied solar power plants in Bangladesh, which will play an important role in achieving Government’s target of 10% supply from renewable sources by 2020 as stipulated in Renewable Energy Policy, 2018. At the request of the Government, the World Bank and KfW are considering credit support to IDCOL for financing Rooftop and Grid-Tied Solar Power Plants.
- IDCOL considers identifying and mitigating environmental & social risks as imperative under its all projects and programs. Accordingly, IDCOL developed two separate environmental & social (E&S) guidelines namely Environmental and Social Safeguard Framework (ESSF) and Environmental and Social Management Framework (ESMF). ESSF deals with infrastructure projects financed by IDCOL while ESMF is used for renewable energy projects/programs. However, the scope of ESMF does not include solar rooftop and grid-tied solar power projects.
- Consequently, as per suggestion of the World Bank, IDCOL has developed a separate E&S guideline titled “Environmental and Social Management System (ESMS)” particularly for grid connected solar and rooftop solar projects in line with the environmental and social risks associated with those projects.
- This document outlines the principles upon which the ESMS is based on, the laws and policies to be followed, the organizational framework and capabilities of IDCOL, environmental and social risks associated with these projects (solar rooftop and grid-tied solar power project), impacts of those in their areas of influence and ways to prevent/minimize those risks or processes to mitigate and manage their adverse impacts. All these aspects are discussed in detail in different chapters of the document.
- Chapter 2 discusses the principles of ESMS. The document is guided by five principles rooted in IDCOL’s Environment and Social Policy Statement which are: (i) to mainstream environmental, health/safety and social considerations with a view to avoid or minimize adverse environmental impacts on people and environment; (ii) to ensure compliance with applicable laws and regulations; (iii) to avoid/minimize land acquisition and resettlement; (iv) to ensure justified and upfront payments and benefits in case of resettlement; and (v) to protect interests of vulnerable groups and tribal communities.
- Based on these policy statement, several principles have been adopted which have been categorized into the following:
- environmental and social risks, impact assessment and management
- environmental health and safety
- biodiversity conservation
- conservation of world heritage
- resettlement
- gender equality and social inclusion
- ethnic communities/ tribal people
- stakeholder engagement
- Grievance redress mechanism
- Chapter 3 discusses about relevant laws and policies which include the following:
- The Bangladesh Environment Conservation Act (ECA), 1995
- Environment Conservation Rules (ECR), 1997
- The Bangladesh Environment Conservation (Amendment) Act, 2010
- Renewable Energy Policy of Bangladesh, 2008
- Guidelines for the Implementation of Solar Power Development Program, 2013
- Remote Area Power Supply System (RAPSS) Guideline, 2007
- Bangladesh Labour Act, 2006
- Bangladesh Factories Act, 1965
- The Building Construction Act, 1952
- The Acquisition and Requisition of Immovable Property Ordinance, 1982
- OP 4.01 Environmental Assessment of the World Bank
- Chapter 4 covers organizations capacity and competency of IDCOL in ensuring compliance with the requirements stipulated in ESMS during implementation and operation of solar rooftop and grid connected solar projects.
- Chapter 5 discusses in detail about the processes and methodologies to be followed in identifying the potential environmental and social risks associated with implementation of solar rooftop and grid-tied projects. It also discusses the possible impacts of those risk and ways to prevent/minimize those risks or processes to mitigate their adverse impacts.
- Notably, large scale grid connected solar and rooftop solar projects fall under Red and Orange A categories, respectively as per Environment Conservation Rules, 1997 of Bangladesh and fall under Category B (limited adverse environmental and social impacts) as per the World Bank’s Safeguard Policies OP/BP 4.01 Environmental Assessment. The projects under these categories require development of ESIA/ESA and periodic monitoring of environmental and social impacts of the projects.
- The ESMS establishes a mechanism to determine, assess, mitigate and manage future potential environmental and social impacts from the activities of solar rooftop and grid connected solar projects during implementation as well as operation.
- The Solar roof-top project will not impact any building of heritage significance (for example, mosque, heritage sites or cultural sites) in Bangladesh or cause any loss to biodiversity or natural habitats. There will be no land acquisition resulting involuntary resettlement or will not create any social conflicts (like; Tribal peoples/Small Ethnic Community issues). However, there may be situations where a neighboring property’s tree (including protected species) may hinder the solar panel operation which needs to be cut down. Also, Neighboring properties may be affected due to sunlight reflection from the panels - If the panels are angled towards windows, doors or a balcony. If the reflection affects the neighbor’s for a prolonged period of the year, it may become a source of grievance. This project does not create any impact on the physical environment like air, water (surface & ground water) and noise. The availability and use of personal protective equipment to follow the environmental health and safety compliances would need to be closely monitored continuously during the constructional and operational phases.
- The Grid-Tied Solar Power Project shall be appraised based on the step-by step process beginning with the primary environmental and social screening stage which measures the impacts requiring appropriate mitigation measures. An Environmental impacts assessment need to be carried out considering present environmental setting of the project area, and nature and extent of the proposed activities. Potential environmental impacts associated with the proposed project activities are classified as:
- Impacts during pre-construction- associated with the land use only
- Construction phase- the major impact associated with the biological environment, physical environment (like; air, noise, water, soil quality) and human environment.
- Impacts during operation phase- main impact is associated with heat generation. The heat may be transferred by convection, radiation and conduction method.
|
|
 |
|
|
|
June 30, 2018 |
|
Annual E_S Compliance Audit Report |
|
|
|
May 4, 2018 |
|
Environment & Social Impact Assessment of Nutan Bidyut (Bangladesh) Limited |
|
|
|
November 15, 2017 |
|
Environment & Social Impact Assessment of Ispahani Summit Alliance Terminals Limited |
|
|
|
September 10, 2017 |
|
Half-Yearly Report (February to August 2017) for Warranty Expired Batteries collection and distribution of new battery in IDCOL SHS Program |
|
|
|
September 10, 2017 |
|
ANNUAL - COMPLIANCE STATUS REPORT OF BATTERY SUPPLIERS AND RECYCLERS OF IDCOL SHS PROGRAM. YEAR 2016-17 |
|
|
|
June 30, 2017 |
|
Annual E_S Comp. Audit Report _Lakdhanavi Bangla Power Limited_2016 |
|
|
|
June 30, 2016 |
|
Annual E_S Compliance of Audit Report_Lakdhanavi Bangla Power Limited |
|
|
|
May 31, 2016 |
|
Environmental and social safeguard compliance of 110 MW HFO based power plant of Summit Barisal Power Limited |
|
Summit Barisal Power Limited (SBPL) has been awarded to design, engineer, manufacture, finance, construct, complete, permit, test, commission, insure, own, operate and maintain a 110 MW Power Plant to generate and supply electricity to Bangladesh Power Development Board (BPDB) for a period of 15 years as an Independent Power Plant (IPP). Considering the importance of the project to meet the power demand, Infrastructure Development Company Limited (IDCOL) along with some other multilateral financial institutions is considering to finance the project.
According to the Environment Conservation Rules, 1997 of Bangladesh Government, industrial projects in Bangladesh have been categorized into four classes—Green, Amber A, Amber B and Red. Considering the magnitude of generating pollution, power plant project has been classified as Red Category project. So, SBPL project has fallen into Red category. According to the Safeguard Policy statement, 2009 of Asian Development Bank (ADB), power plant project of about 110 MW capacity falls into category B due to the localized impact. As a part of environmental compliance, there is a requirement for preparation of an Environmental Impact Assessment (EIA) according to ECR, 1997 of Department of Environment (DOE) and Initial Environmental Examination (IEE) report according to SPS, 2009 of ADB. The content of IEE of ADB is almost similar to EIA of DOE, except the public consultation aspects as is required by ADB. SBPL has already engaged Bangladesh Centre for Advanced Studies (BCAS) to prepare the IEE according to the requirement of ADB as well as the DOE.
NOx, SOx, noise and lube oil are the main issues to consider from environmental pollution perspective of the said power plants. As a guiding standard, SBPL has to comply with the national standards of Bangladesh. Where national standards are not available, SBPL has to comply with the best practices like ‘Environmental, Health and Safety Guidelines of IFC’.
IDCOL is careful about maintaining environmental and social safeguards. It encourages all, having any complain or observation regarding any matter of the Projects, to contact IDCOL management.
For the Environmental Impact Assessment Report please click on the link below:
|
|
 |
|
|
|
May 31, 2016 |
|
Environmental and social safeguard compliance of 55 MW HFO based power plant of Summit Narayangonj Power Unit-II Limited |
|
Summit Narayangonj Power Unit-II Limited (SNPU2L) has been awarded to design, engineer, manufacture, finance, construct, complete, permit, test, commission, insure, own, operate and maintain a 55 MW Power Plant to generate and supply electricity to Bangladesh Power Development Board (BPDB) for a period of 15 years as an Independent Power Plant (IPP). Considering the importance of the project to meet the power demand, Infrastructure Development Company Limited (IDCOL) along with some other multilateral financial institutions is considering to finance the project.
According to the Environment Conservation Rules, 1997 of Bangladesh Government, industrial projects in Bangladesh have been categorized into four classes—Green, Amber A, Amber B and Red. Considering the magnitude of generating pollution, power plant project has been classified as Red Category project. So, SNPU2L project has fallen into Red category. According to the Safeguard Policy statement, 2009 of Asian Development Bank (ADB), power plant project of about 110 MW capacity falls into category B due to the localized impact. As a part of environmental compliance, there is a requirement for preparation of an Environmental Impact Assessment (EIA) according to ECR, 1997 of Department of Environment (DOE) and Initial Environmental Examination (IEE) report according to SPS, 2009 of ADB. The content of IEE of ADB is almost similar to EIA of DOE, except the public consultation aspects as is required by ADB. SNPU2L has already engaged Bangladesh Centre for Advanced Studies (BCAS) to prepare the IEE according to the requirement of ADB as well as the DOE.
NOx, SOx, noise and lube oil are the main issues to consider from environmental pollution perspective of the said power plants. As a guiding standard, SNPU2L has to comply with the national standards of Bangladesh. Where national standards are not available, SNPU2L has to comply with the best practices like ‘Environmental, Health and Safety Guidelines of IFC’.
IDCOL is careful about maintaining environmental and social safeguards. It encourages all, having any complain or observation regarding any matter of the Projects, to contact IDCOL management.
For the Environmental Impact Assessment Report please click on the link below:
|
|
 |
|
|
|
February 10, 2016 |
|
Minutes of the Quarterly Compliance Meeting with the Battery Manufacturers and Recyclers held at IDCOL Office on 4 February 2016 |
|
|
|
April 15, 2015 |
|
Observation report for environmental, social and health safety compliance of three Solar Irrigation Project (Operational) April 2015 of MAZAND Consortium Ltd. (MCL) |
|
|
|
July 22, 2014 |
|
Quarterly EHS Compliance Report for the Battery Recyclers |
|
|
|
March 18, 2014 |
|
Environment & Social Impact Assessment of Lakdhanavi Bangla Power Limited |
|
|
|
January 1, 1970 |
|
Environmental and Social Safeguards Framework Arrangement : Third PublicPrivate Infrastructure Development Facility Tranche 2 |
|
|
|
|
|
|
|